Contractor needed 780 bags of OPC 53 cement delivered across three pour dates with no site-storage space. A single large delivery would have blocked road access and damaged the unset slab.
BuildingNeeds split the order into three scheduled deliveries — 260 bags each on Monday, Wednesday, and Friday — timed around pour schedules. GST invoice issued per dispatch.